Hi,
I'm working on PS BOM for one of the requirement. Steps that are carried are as below and we are facing problem when confirming finished header material into project stock along with consuming component.
Steps:
- Created a simple project with root level WBS and one child WBS. Under it we have network header and activity with reference point 10.
- Created material and BOM : material BOM Main(FERT) with component under it BOM sub1(HALB) and BOM Sub2 (HALB). under BOM Sub1 assigned sub component BOM Sub11 (HAWA).
- Released the project.
- Ran CN33 with material BOM Main along with child WBS. (Unchecked Multilevel and All items) along with had BOM Main in transfer control with reference point 10.
- This created 3 material component in network . i.e. for material BOM Main ( with -1PC qty), BOM Sub1 (with 1PC qty) and BOM Sub2 (with 1pc qty)
- Note for all the material backflush is 1 hence on procurement view too backflush are checked.
- Run MD51, which created plan order for BOM sub1 along with BOM Sub11 as dependent requirement and plan order for BOM Sub2.
- Completed the cycle of procurement of all this 3 material where BOM sub11 for consumed in BOM sub1.
- Now I find material stock of 1 qty in child WBS for BOM sub1 and BOM sub2.
According to few earlier thread I came to know that after confirmation of activity auto GR happens for main material BOM main and also it consumes other components resulting stock of BOM main.
But on confirming the activity no auto GR not consumption of component is happening for me.
I'm I missing setting /configuration? please let me know
Regards,
Pradeep