Go to OPU7 change the Adjust dates "Do not adjust basic dates, depent requirements to operation dates"
After this, you should be able to update the basic start and basic finish dates.
Regards
Terence
Hi,
Go to OPU7 change the Adjust dates "Do not adjust basic dates, depent requirements to operation dates"
After this, you should be able to update the basic start and basic finish dates.
Regards